News

PDD to factor curtailment agenda subsequent week:Extra energy cuts in offing

SRINAGAR, NOV 23,
2019: Consultant to Lieutenant Governor, Ok.Ok Sharma as of late chaired an intensive
submit snowstorm overview assembly with the officers of Energy Construction Division
(PDD)—directing officials to be informed courses from the demanding situations and stay
ready a lot upfront.

Addressing the
officials right here in Srinagar, the Consultant steered officials of PDD and its allied
wings to head for evaluation of the damages and do the re-structuring of the
division and its allied wings. He directed the officials to paintings in shut
coordination for fending off any eventuality in view of the inclement climate.

Leader Engineer,
PDD, Distribution, Kashmir, Hashmat Qazi, Leader Engineer, Transmission, Aijaz
Ahmad Dar, SEs X-ens, Monetary Consultant (PDD), amongst different senior officer of
the dep. attended the assembly.

 

Consultant Sharma
stated that herbal calamities be offering a studying procedure for the management.
“We should sit down and introspect as to be informed from screw ups,” he stated.

Previous, the
officers knowledgeable the assembly that all through summers, PDD equipped 24×7 energy
provide to each to metered in addition to unmetered customers, excluding for a only a few
localized spaces with machine constraints. It used to be knowledgeable that on a mean,
the dep. has been supplying height load of 1200 MW and in local weather, the
division confronted problem of supplying higher load, which regularly surges
from onset of autumn and peaks in iciness.

Leader Engineer,
PDD (Distribution), Kashmir, Hashmat Qazi knowledgeable the assembly that at the present,
‘Height Load’ of round 1750 MW is being encountered all through night time top
hours.  He stated that this iciness, the
division is anticipating unrestricted height call for of 2000-2100 MW.

He stated that due
to the limitations at grid, transmission degree the dep. in fresh previous
has been supplying height load of 1250 MW. Then again, with the optimum usage
of to be had assets and shut coordination PDD has been serving further
load of 100 MW all through height hours, thereby expanding the full load served to
1350 MW.

Leader Engineer,
PDD (Transmission), Aijaz Ahmad Dar knowledgeable the assembly that underneath
development Zainakoot-Alestang Transmission line passed off huge damages in
fresh snowstorm by way of inflicting harm to 10 necessary towers. He alternatively knowledgeable that
a complete contingency plans had been interested in paintings once more on battle footing
foundation. He stated in a similar fashion 132KV Badampora-Bandipora line too suffered large tower
harm and line paintings will serve as once more after repairing of broken towers.

Energy State of affairs
& Curtailment

In its undertaking
to care for solid energy provide all through winters, when the height call for is
forecast as 2000-2100 MW, PDD is constrained to implement load losing of round
700-750 MW.

The assembly used to be
knowledgeable that with the commissioning of 220 KV ring line connecting Zainakote
grid and Aulesteng Grid at 220 kV degree, the Town grids: Waganpora,
Habbak,  Cheshmashahi and Pampore Grid
will have the ability to feed  further energy to
the order of 200 MW to Srinagar and different adjacent  spaces, thereby lowering the infrastructure
constraint and minimizing the curtailment hours within the Town.

The assembly used to be
knowledgeable that to be able to steer clear of unscheduled cuts because of constrictions of
current infrastructure at 33 kV degree and under, Up-gradation of seriously
overloaded 33 kV feeders & Receiving Stations is being performed underneath
quite a lot of centrally backed schemes like PMRP / DDUGJY /IPDS.

Established order of
Keep an eye on Rooms
The assembly used to be
knowledgeable that status quo of keep watch over rooms and buffer stocking of subject matter to
meet any eventuality because of antagonistic climate and calamity and 5 Keep an eye on Rooms
had been established to coordinate the recovery procedure at main Grid
Stations around the valley.

Leave a Reply

Your email address will not be published. Required fields are marked *

This site uses Akismet to reduce spam. Learn how your comment data is processed.

Back to top button
%d bloggers like this: